This project involved the installation and commissioning of a new 33kV underground Sub Transmission line/Circuit from Powerco Linton Sub Station to Powerco Turitea Sub Station.

Clarke Underground was subcontracted by Downer NZ to undertake the project. This was a direct bury (trenched) installation of the primary cable with the added complication of a portion of drill shot duct installation. Directional Drilled approx. 100 metres of 3 x 150mm and 2 x 50mm ducts at a 37% degree angle up the bank.

Trenching works included sand bedding (100mm) and another layer of sand cable cover (100mm) then ground compaction and grassed.

Client

Powerco & Downer NZ

Machinery

JT32, Excavator, HydroVac

Location

Powerco Linton Sub Station – Powerco Turitea Sub Station

2023

Installed and commissioned 33kV underground line from Linton to Turitea, including trenching and directional drilling.